A Simple Example Of A Definition Of Done

A Simple Example Of A Definition Of Done

At a recent class, a new Scrum Master asked me for a simple example of a Definition of Done. They also wanted to understand how it differed from the concept of acceptance criteria. This post captures my answer to them and I hope it will help simplify this concept for you. First some explanations of what these terms mean.

Acceptance criteria are an optional but commonly used complementary practice to Scrum. They are a set of statements that describes the conditions that work must satisfy in order to be accepted by a user, customer, or other stakeholder. Acceptance criteria increase transparency around what is required to complete a piece of work to someone’s satisfaction.

The Definition of Done is part of Scrum. It is a commitment to the Increment and provides a formal description of the state of the Increment when it meets the quality measures required for the product. The Definition of Done increases transparency by providing a shared understanding of what work was completed to a minimum level of quality. And now for that simple example:

We run a Bakery. Our product is baked goods sold in our shop to passing customers. We have 2 items to create that are currently in our Product Backlog. They have acceptance criteria defined to help us understand aspects of the work that needs to be carried out. Here they are:

Product Backlog item 1 – Baguettes
Acceptance Criteria:

  • At least 18 inches long and 2 inches in diameter.
  • Golden brown all over after cooking.

Product Backlog item 2 – Iced Buns
Acceptance Criteria:

  • At least 5 inches long and 3 inches high.
  • Icing covers at least 80% of the top of the bun and it has a Cherry on top.

Acceptance criteria are at the micro-level and are unique and specific to each Product Backlog item. The criteria here ensure we have understood the work for each item and that we have met someone’s needs with the completed work.

Our Definition of Done would apply to both of these items before they could be considered part of an Increment that we would put on sale to customers. Here it is:

Definition of Done:

  • All ingredients used were fresh.
  • The kitchen was clean at the time of preparation.
  • The product has been visually inspected after cooking and is attractive and defect-free.
  • 1 product in each batch has passed a taste test before the batch is put on sale.

The Definition of Done is at the macro level and is applied to all Product Backlog items before they can be considered part of an Increment. The criteria here ensure a known level of quality has been reached, regardless of what specific work was carried out.

In this example, we can see that it would not make sense to give a product to a customer that did not meet our Definition of Done. An inferior product could mean we lose the customer, hurt the customer or get our Bakery closed down. Making quality criteria transparent and applying them to all our product Increments helps ensure this does not happen.

Unfortunately when people create less tangible products like software, quality is harder to inspect and so people are more likely to overlook it. Scrum’s Definition of Done is intended to prevent this from happening.

Do You Want To Learn Scrum & Agile?

Learn Scrum & Agile at lost cost and online. Our 5-star rated Ultimate Scrum & Agile eLearning Courses can take you from beginner to advanced at your own pace.

Prepare and practice for the assessments from the major Scrum & Agile providers. Our 5-star rated Ultimate Scrum & Agile Practice Assessments will help you gain certification.

About TheScrumMaster.co.uk

Hi, my name is Simon Kneafsey and I am a Professional Scrum Trainer with Scrum.org and TheScrumMaster.co.uk. I am on a mission to simplify Scrum & Agile for 1 million people. I have helped 10,000+ people so far, and I can help you too. Find out more & get in touch.

Recent Posts

Comments 2

  1. Hi Simon

    thanks for that blog post -really enjoyed reading! I have a question regarding your Acceptance Criteria in the examples. Specifically the ones with:
    “Cooked for 15 minutes at 200 degrees. ” or “Cooked for 20 minutes at 220 degrees.”
    Isn´t this more about the part on how to reach “Golden brown all over after cooking.”?
    As a customer, I wouldn´t be able to judge if it was cooked for 15min at 200degrees, therefore I can´t check the acceptance criteria. But I could judge the golden brown.
    My question: wouldn´t these criteria more be a part of the “solution approach”, so how does the baker reach the acceptance criteria?
    Hope you got my questions, all the best
    Dominik